Electrical Control of Industrial Mechanisms · PLC-200 trainer · S7-200 CPU 224
Lab work report
One report per group. Attach the program listing printed from STEP 7-Micro/WIN. The “Initials” boxes are signed by the instructor during the session. Grey italic text is an example: replace it.
The group
| Full name | Student ID | Role at the bench | Signature |
|---|
Roles: programmer, tester (operates the bench and fills in the log), reporter. Swap roles from one lab to the next.
Preparation
/ 3Done before the session. For each preparation question: the answer, the working, the value and its unit.
Functional analysis
2.1 Input / output and symbol table
2.2 GRAFCET
Draw or paste the GRAFCET here (numbered steps, transition conditions written with the symbols, actions to the right of the steps).
2.3 Internal resources used
Program
/ 6Attach the ladder listing and the symbol table printed from Micro/WIN. Here, the map of the program: one network per row.
Test log
Write the expected result before the test, then what you observe on the bench.
Signed checkpoints
The instructor signs after a group member who did not program the network explains it.
Fault injection
bench / 6Every fault listed in the lab sheet is really provoked. A fault must stop the machine, never start it.
Discussion
/ 5Group declaration
Marking grid
instructor| Part | What is assessed | Mark |
|---|---|---|
| Preparation | I/O table and GRAFCET correct before the session, preparation calculations | |
| Program | Behaviour; symbols, SCR steps, comments | |
| Bench demonstration | Functions shown; every fault-injection test ends in a safe state | |
| Report | Complete, clear, tables filled in and signed, answers justified |